As a result of previous research and conclusions of the Feasibility Study of Zijin Bor Companies Copper decided to open an underground copper mine along with ancillary ore processing and mineral concentration plants as well as disposal facilities tailings. In accordance with the reserves of the copper and gold ore deposit, “Čukaru Peki” was adopted production and processing capacity of 10,000 t / day, or 3.3 Mt of ore per year.
The project envisages underground exploitation of ore and preparation on the surface mineral resources, disposal of tailings and construction of other ancillary facilities such as: electricity supply and distribution, water supply and drainage, system for paste application, communications, internal and external transport, and more.
Consortium Faculty of Civil Engineering, University of Belgrade and CPM Consulting doo Belgrade supervises the project.